In this document we will discuss what is the Permit and what are the types of it (Technical Permit)

 

Note: The below steps are applied on SAP ECC6.0  EHP6.0

 

Table OF Contents:

1- Introduction

2- Technical Permit

2.1 Create the Technical Permit

2.2 Assign The Technical Permit To The Technical Object

2.3 Technical Permits Influences The order

 

1- Introduction

Permits are created for the Maintenance Order to:

  1. Adhere to health and safety regulations
  2. Control order processing (Release – Completion<TECO>)

 

There are two types of permits:

  1. Technical Permits (assigned manually to the technical objects (Equipment – Functional Location)

   2. Process-Oriented Permits (automatic assignment to the order)


2- Technical Permit

Steps:

  1. Create The Technical Permit
  2. Assign the Technical Permit To The Technical Object
  3. Technical Permit Influences The Order

 

2.1 Create The Technical Permit

 

SAP ECC Menu: Logistics -> Plant Maintenance -> Management of Technical Objects -> Environment -> Permits

T Code: IPMD

 

Click On (Create/Change) Button To Enter The Change Mode

1_783082.jpg

 

Then

 

2_783372.jpg

 

/wp-content/uploads/2015/09/3_783373.jpg

4_783383.jpg

 

Note: We Will Work On Order release

 

2.2 Assign The Technical Permit To The Technical Object

Note: We Will Assign The Permit To An Equipment -> T Code: IE02

/wp-content/uploads/2015/09/5_783393.jpg

6_783394.jpg

7_783401.jpg

 

You can assign more than one technical permit to the equipment

 

2.3 Technical Permits Influences The order

When Creating a maintenance order for the equipment which the permit has been assigned to it:

1- If you used the 1st option in the permit (Permit to be issued after warning)

when you release the order, a warning message appears but if you pressed Enter, you can continue processing the order

/wp-content/uploads/2015/09/8_783404.jpg

2- If you used the 2nd option in the permit (Permit Must be issued else Error Message)

The order can not be released until the authorized user issue the permit

9_783405.jpg

 

10_783408.jpg

 

11_783409.jpg

 

12_783413.jpg

 

3- If you used the 3rd option in the permit (Permit Must not be issued )

No Warring Message,  just check the permits  From The permit Button

13_783414.jpg

 

Note: (I_Sogen) is the authorization object related to the permit (The User that will issue the permit)

Note: The authorized user can reverse the Permit (Cancel the issue) only before the order being Released or TECO (Depend on your settings)